[KWartzAnnounce] IMPORTANT: Notes for people doing the buildout
KWartzLab Members Announce List
announce at kwartzlab.ca
Wed Aug 19 23:21:33 EDT 2009
Hi everyone,
Two important notes for people doing the buildout:
1) Do not cut into the walls at all without checking with me first.
There may be lease compliance issues, so we don't want to run afoul of
them. Patching walls is fine, sanding and taping is fine, painting is
fine, but do not remove any drywall or other wall covering without
checking with me personally first.
2) Two of the outlets have been marked "Rev Pol" because they have
reversed polarity. Do not use them.
That is all. Continue making the hackerspace!
Cheers,
Eric